L68A1 Mast Section This paper mainly explains the steps and precautions of the operation test of the tower crane connecting the main circuit

04-12-2019

This paper mainly explains the steps and precautions of the operation test of the tower crane connecting the main circuit. Part of the content of this station comes from the network and is only for reference. If you have any questions, please contact us. We will try our best to answer them. 


① operate each mechanism of the tower crane respectively, observe the height limit, trolley travel limit, crane travel limit and rotation limit, and check whether the limit switch is consistent with the running direction, and can accurately operate the power-off, otherwise it should be adjusted.

L68A1 Mast Section:

http://www.towercranesupply.com/product/l68a1-mast-section-for-tower-crane-mastsL68A1 Mast Section





② conduct a comprehensive inspection on the wires, cables and their connections of all parts of the whole machine. Especially at the joint, bend and contact with high temperature of the wire, strengthen the inspection. These places are most likely to break the wires and damage the power supply, so it is necessary to focus on the inspection and timely handle or replace the new wires and cables in case of any hidden danger.




③ make each motor run in turn to check whether it starts and runs smoothly and normally, and whether there is noise. At the same time, observe the speed regulation of multi speed motor and slip ring motor. If any problem is found, find out the cause and solve it.


L68A1 Mast Section:

http://www.towercranesupply.com/product/l68a1-mast-section-for-tower-crane-masts

L68A1 Mast Section


④ respectively move the controller of hoisting, slewing, trolley and crane to check whether the operation direction is consistent with the actual operation direction. If not, adjust it.