L68B1 Mast Section Data required for tower crane foundation design, safety inspection application, etc

12-12-2019

Design and construction scheme of tower crane foundation (detailed construction drawing and layout plan of tower crane foundation):


L68B1 Mast Section:

http://www.towercranesupply.com/product/l68b1-mast-section-for-tower-crane-mastsL68B1 Mast Section




1. Process quality inspection application form;


2. Quality acceptance record of inspection lot of reinforcement sub divisional works (raw materials, reinforcement processing);


3. Acceptance records of concealed works;


4. Quality acceptance record of inspection lot of concrete sub items (raw materials, mix design);


5. Quality acceptance record of inspection lot of concrete sub item (concrete construction);


6. Acceptance record of cast-in-place structure sub project (structure construction);


7. Foundation trench inspection record and foundation treatment record


8. Quality certificate inspection report of embedded parts




Relevant safety disclosure, technical disclosure and other information:



L68B1 Mast Section:

http://www.towercranesupply.com/product/l68b1-mast-section-for-tower-crane-masts

L68B1 Mast Section

1. Qualification of installation unit


2. Personnel certificate


3. Acceptance record


4. Installation plan


5. Tower crane foundation construction drawing


6. Foundation bearing capacity report


7. Tower crane certificate and operation instruction


8. Quality assurance data of tower crane foundation construction




The safety inspection application materials of tower crane include:




1. Inspection application: after the tower crane is installed, go to the safety supervision station to handle the relevant procedures, pay the inspection fee and request the inspection. Waiting for the inspection report to be issued; you need to provide the copy of the business license of the tower crane manufacturer, the purchase and sale contract, the supervision and inspection report, and the original of the product certificate.


2. Handling the use registration procedures: bring the inspection report, collect the form at the safety supervision station, handle the relevant data, submit it to the safety supervision station, obtain the "permit" after approval, the tower crane can be put into use, and put on record as a hazard source, and cancel the number after use and demolition.


3. Accessories required: list of tower crane, registration certificate, inspection certificate, registration form of construction crane, acceptance inspection report, disassembly plan, jacking plan, anchoring plan, safety technical disclosure, grounding test record, installation and commissioning record, foundation acceptance form, installation acceptance form, anchorage acceptance form, inspection record, hoisting machine acceptance form, operator registration Table, work license of special personnel, work safety agreement, management system of mechanical installation and use, qualification certificate of installation unit, etc.


4. Production license, installation unit qualification and production unit qualification of tower crane.

L68B1 Mast Section:

http://www.towercranesupply.com/product/l68b1-mast-section-for-tower-crane-masts

L68B1 Mast Section