256HC Mast Section Safety problems when the tower is mounted

05-11-2019

For tower lifting equipment, some problems should be noted when erecting tower bodies.
The electrical equipment such as controller and limited-position switch should be inspected. The active control disk in the operating room should be removed and installed on the outdoor bracket to facilitate the operation of the tower.


Tighten the rail clamp and wedge the Anti-Slip wedge under the running wheel. In order to strengthen the stiffness of the door frame, cross supports can be tied on both sides of the door frame. Before moving around, the duties of each post should be stipulated, strict division of labor and command and liaison signals. The inspection of the main ground anchor should be the responsibility of an experienced crane. When an abnormal phenomenon such as looseness is found, immediately stop to take measures(additional iron pressure can be added to the ground anchor).
Start the hoist, so that the tower body left around 200 mm to the wooden stack, immediately stop, check the force of the components in good condition.

256HC Mast Section 

256HC mast section the specification can suitable this situaton no problem .


Get the latest price? We'll respond as soon as possible(within 12 hours)

Privacy policy