256HC Mast Section Briefly introduce the preparation work, installation steps and operation points of tower crane installation

09-12-2019

(1) preparation



256HC Mast Section:

http://www.towercranesupply.com/product/256hc-mast-section-liebherr-tower-crane256HC Mast Section



Check whether the subgrade and track laying meet the requirements, bury the ground anchor, and determine the position of the ground anchor according to the rotating lifting direction of the tower and the total height of the tower body.




(2) overall installation




According to the procedures required in the manual, install the traveling mechanism, gantry and pressing iron. Insert the lifting arm on the support shaft of gantry platform, build the wooden pier according to the assembly dimension of the tower body lying down, and assemble the tower body and tower cap, so that the tower body is on the wooden pier, and its axis is roughly parallel to the ground.




(3) wire rope threading


256HC Mast Section:

http://www.towercranesupply.com/product/256hc-mast-section-liebherr-tower-crane

256HC Mast Section


The hoist wire rope is fixed at the head of the crane through the pulley block from the cab to the tower cap. The total length of the rope and the distance between the two pulley blocks shall be determined by calculation.




(4) in front of the tower




The controller, limit switch and other electrical equipment shall be inspected, and the movable control panel in the control room shall be removed and installed on the outdoor support to facilitate the operation when the tower is erected.




(5) erect the tower body




After inspection, it is confirmed that the situation is normal. Continue to start the winch to make the tower body stand stably, and the steel wire rope at the auxiliary ground anchor will be loose.

256HC Mast Section:

http://www.towercranesupply.com/product/256hc-mast-section-liebherr-tower-crane

256HC Mast Section